Concentrator equipment, spare parts, accessories acceptance system

1. Purpose

In order to improve the quality of spare parts, extend equipment maintenance cycle, and reduce equipment maintenance costs, these measures are formulated in accordance with the company's spare parts management regulations.

2. area

This approach is suitable for beneficiation plant equipment, spare parts acceptance purposes.

3. Composition of the inspection personnel

The company's material supply department, the relevant technical personnel of the mobile department, the equipment leader of the ore dressing plant, the equipment manager, and the person in charge of the use unit.

4, with experience collection methods:

4.1 After the equipment arrives at the factory, the model will be checked first according to the relevant procurement plan. If it does not meet the planned model, it will not be accepted or put into storage.

4.2. For the quality problems existing in the acceptance, detailed records shall be recorded, and the purchasing unit shall be notified, and after consulting the specific circumstances, report it in writing.

4.3. The equipment to the factory must be accompanied by detailed information such as the specification, certificate, and related drawings. Otherwise, the income bank will not be examined. In special cases, the supply department will be responsible for recovering the relevant materials, but it must be recorded.

4.4. When the equipment in the factory has serious appearance damage, it shall be recorded and photographed by the supply department, and the original reason shall be explained to the manufacturer to avoid unnecessary damage caused by transportation accidents or other causes of equipment damage and quality. Loss and trouble.

4.5. The acceptance of exquisite spare parts and accessories is mainly the model and appearance quality. For spare parts with blisters and rough appearance, it should be recorded in detail. If it cannot be used, it must be returned to the supplier.

4.6. When the pipe and steel are inspected, check whether the caliper is consistent according to the planned model. The appearance is whether there is serious damage or deformation, especially the plastic products. If there is serious damage, it will not pass the acceptance.

5. After the acceptance is completed, the relevant personnel must sign and approve the equipment acceptance form, otherwise it will not be put into storage and use.

Concentrator equipment, spare parts inspection and acceptance